Release Planning      V1 Menu

agile insight
Release Planning is the activity that Agile teams undertake to determine how much scope will be completed within a given timeframe. The stories and/or backlog items that are assigned to a release are estimated by the development team. The prioritized release plan is then used as input into planning a series of smaller iterations of work. Release planning takes place at the beginning of a project, but then recurs at intervals throughout a project in order to course-correct based on customer feedback, team velocity and any new information. Ideally release schedules should be kept short in duration in order to facilitate as many functional releases as possible within a given period. The goal of the release plan is to communicate which features will be delivered by the release deadline.
 

V1 Release Planning Step-by-Step

(Optional) Schedule Release

release planning overview
watch product planning video       

The Release Planning process is used to move backlog items and defects through the project hierarchy.

  • Select Release Planning in the main menu.

  • Schedule backlog items and defects in releases by clicking and dragging a row in grid at the bottom up into the appropriate Release (sub- project) container above.

  • To remove backlog items or defects from a release, display the detailed list in the release container, then click and drag a row from the container into the larger project container that surrounds the entire top section of the page.

  • To move backlog items or defects from one sub-project to another, drag the row from the detailed list into another sub-project container on the page.

(Optional) Schedule Teams

team scheduling overview
watch team scheduling video       

The Team Scheduling page is used to allocate workload across the various teams working on the project.

  • Select Release Planning in the main menu.

  • Select the Team Scheduling page.

  • Assign backlog items and defects to a team by clicking and dragging a row in grid at the bottom up into the appropriate Team container above. If the team is not visible, you can also drag onto a row of the All Teams list at the left to make the assignment.

  • To remove backlog items or defects from a team, display the detailed list in the team container, then click and drag a row from the container into the larger project container that surrounds the entire top section of the page.

  • To move backlog items  or defects from one team to another, drag the row from the detailed list into another team container on the page.

Next-> SprintPlanning