V1 Sprint Planning Step-by-Step
Establish a Project Schedule
Sprint Scheduling is the first step in the Sprint Planning process. Sprint
Scheduling allows the project team to select a list of backlog items to be
delivered within the sprint. Sprint Scheduling can also optionally be used to
schedule work on specific defects within the sprint.
sprint planning overview
Select Sprint Planning in the main menu and the Sprint Scheduling
page in the sub-menu.
Set project context to the appropriate scheduling project.
If not already done, assign or create a new iteration schedule for
the project.
Enter sprints by selecting Add.
(Optional) Plan Expected Team Member
Capacity
capacity planning overview
If not already done, enable Capacity Planning in the system by
selecting Administration in the main menu and Configuration in the sub-menu
and turning on the feature using the System page.
Select Sprint Planning in the main menu and the Capacity Planning
page in the sub-menu.
Use the historical reporting to gauge each team member's historical
capacity and factor in any known impacts (training, holidays, etc.) for the
upcoming iterations.
Enter capacity for each team member in terms of Detail Estimate
expected to be completed.
Schedule Backlog Items and Defects in
Sprints
Select Sprint Planning in the planning menu and the Sprint Scheduling page in
the sub-menu.
Assign backlog items and, optionally, defects to sprints by clicking
on a row in the grid and dragging it up into the appropriate Sprint
container above. View the Detailed Listing to see the individual items in
the sprint.
To remove backlog items or defects from sprints, view the Detailed
Listing for the sprint container and drag the appropriate row out of the
container into the surrounding space.
To move backlog items or defects from one sprint to another, view the
Detailed Listing for the current sprint and drag the appropriate row to
another sprint in the display.
Activate Current Sprint
Detail, Estimate and Assign Backlog
Items, Defects, Tasks to Members
Select Sprint Planning in the main menu and the Detail Planning page in the
sub-menu.
Select Plan Story to add a set of tasks and tests.
Define Detail Estimates for your tasks and tests and identify which
team member(s) has signed up as owner of each.
Once changes have been made, select Apply to save the changes.
Verify Members Work Load
To validate team members' work loads, select Member Planning in the Sprint
Planning sub-menu, and make changes to ownership if appropriate.
View any unowned workitems in the No Owners list at the bottom of the
page.
(Optional) Manage Issues
(Optional) Review and manage issues identified by the team that can hamper team
performance or delivery.
Determine whether any issues require specific work to be done in this
sprint. Generate a backlog item if needed.