Is there a way to back out the "Task Done" time after it has already been applied?  I accidentally entered too large of a number under Effort and now the number being reported under "Done" is way off.

You can back out an erroneous Effort entry by entering a negative number in the Effort column. If you've entered '22' instead of '2' and saved your entry, you can simply enter a '-22' to back the entry out. The system preserves each detailed entry, so you will be able to see both the original and corrective entry in your tracking History.

To review this History, use the Task Quicklist within reports.



last modified: 3/11/2009 12:07 PM