Feature Summary / Major Changes
- Sign Me Up
- Quick Close
- Cruise Control Integration
- IntelliJ IDEA Integration
- Visual Studio 2008 Integration Upgrade
- Bugzilla 3.2 Integration Upgrade
- System Requirements Change
- Miscellaneous
Get the latest Team Edition
New Customers: Sign Up for Team Edition today.
Existing customers: On-demand Team Edition systems will be upgraded automatically. Download an Upgrade for your on-site system.
Sign Me Up
A new action has been added to menus to quickly sign up for tasks, tests, defects or stories. This option is also available in the multi-select action menu to allow a member to sign up for a number of items all at once.
Quick Close
Another new action in the menus has been added to allow team members to quickly update status values and close out an item all at once. The Quick Close is also available in the multi-select action menu to allow a member to close a number of items all at once. The Quick Close will update status values as follows:
- Story: updated to Accepted
- Defect: updated to Accepted
- Task: updated to Completed
- Test: updated to Passed
View the trend of accumulated Effort (Done) over the course of time for an entire project, release, team, program or individual member. Use the Effort Trend report to help understand the cost of project work being completed. This report displays only when Effort Tracking is enabled.
Cruise Control Integration
The CruiseControl integration provides the same functionality that is currently available in CruiseControl.NET. Both integrations provide visibility into the stories and defects included in each build. From a story perspective, build integration indicates which build contains work towards completing a story and which build contains the completed story. From a defect perspective, build integration indicates the build where a defect is found and where the defect is fixed. This visibility is exposed in a Build Contents report which shows a) which defects are fixed, b) which stories are complete and c) any new defects introduced, but not resolved. This report is valuable for selecting a build to release and for creating release notes that summarize work completed for a release.
IntelliJ IDEA Integration
Java developers working in the IntelliJ IDEA IDE can view and update their task work without leaving the IDEA IDE. This integration provides a new view that show the tasks owned by a team member in the current iteration/sprint and allows updates to status and time tracking directly from the IDE. There is also a view that allows the developer to see more details on a selected task and edit these attributes.
Visual Studio 2008 Integration Upgrade
The Visual Studio integration is now available for Visual Studio 2008. This integration allows Visual Studio Developers to view and update their task work without leaving the Visual Studio IDE.
Bugzilla 3.2 Integration Upgrade
The Bugzilla integration now supports Bugzilla 3.2. The VersionOne Bugzilla Integration provides a two-way flow of information between VersionOne and Bugzilla.
- Please note that we changed our integration approach for Bugzilla 3.2. Rather than installing custom scripts on Bugzilla, we now using the Bugzilla Extension mechanism. When you upgrade your Bugzilla instance we recommend that you uninstall and re-install the VersionOne integration.
System Requirements
This release requires Microsoft .Net 3.5 on the web server.
Miscellaneous
- The default action on tracking pages for items with 0 remaining To Do and all closed tasks has been changed from 'Plan' to 'Quick Close' (or 'Close' if Quick Close is disabled).
- The Options under My Projects has been renamed 'Filters'
- The .mpx export now feeds data into the custom text fields in MS Project: Item Number (Text 1), Priority (Text 2), Risk/Complexity (Text 3), Theme/Feature Group (Text 4), Team (Text 5).
- The Sprint scheduling containers dynamically refresh when items are dragged into or between the containers. This no longer causes a full page refresh.
- Our SDK and Integrations now send locale information to the server