Velocity by Date Report
Editions
This feature is available in Catalyst, Enterprise, and Ultimate editions.
Overview
The Velocity by Date report is a bar chart that:
-
shows the total Estimate completed, by Date, over a specified date range (days, weeks, or months).
-
rolls up velocity across different sprint schedules.
Accessing This Report
-
Click the Report icon
on the side bar followed by All Reports.
-
In the Project/Release Reports section or Planning Reports section, click Velocity by Date.
Report Filters/Parameters
- Team: Shows Team-specific data for the project or program. The default value is "All" or "Blank".
- Backlog Group: Shows data assigned to the selected backlog group.
- Workitem: Shows data for a specific work item type: All (all workitems), Stories, Defects, or Testsets. The default option is "All".
- Aggregation Type: Determines how the data is aggregated. Valid values are:
-
Sum of Estimate - Sum of the Estimate values.
-
Workitem Count - Count of work items regardless of estimate value.
-
- Portfolio Item: Shows work items in the selected portfolio item and all of it's children. The default option is "Blank" and shows all work items.
- Start Date: The first date the report begins calculating data.
-
For project-based reports, the default start date is the project start date.
-
For sprint/iteration-based reports, the default start date is the sprint/iteration start date.
-
For member-based reports, the default start date is 13 weeks prior to the current date.
-
If the start date is set to the current date or later, no data displays.
-
- Interval: The length of each interval (days, weeks, or months) you want to show in the report. By default the length+gap as set on the project's sprint schedule. If no schedule is available, it defaults to 2 weeks.
- For projects, the report uses the number of weeks from the project's start date to today.
- For sprints, the report uses the the number of days in the sprint.
- Grouping: Shows the velocity report of the selected grouping.
Technical Details
-
By default, the date range is set to the beginning and ending dates of the project and the duration is set to measure by weeks.
-
If the project has no end date, the end date defaults to the current date.
-
The report considers the work items "Date Completed" attribute when assigning the work item to a period.