How do I see the total effort for a specific task in sprint tracking?

This feature is available in all editions.

editions-all.png

Answer

The Done amount is total effort or the accumulation of all Effort entries. If you are already tracking Effort, the Done amount is a default column on the Detail Tracking page.

To display the default columns:

  1. Select the Customize link on the grid.

  2. Select the Reset Defaults option.

  3. Expand all rows in the grid to see the Done amount on tasks.

If Done and Effort are not displayed within the page after resetting the defaults, it means that Effort tracking is not enabled within your system.