How does VersionOne calculate the forecast completion date?
Editions
This feature is available in all editions.
Related Articles
- How does VersionOne calculate the forecast completion date?
- Interpreting the Release Forecasting Charts
- Is there a way to see the expected finish date of a project?
- Performing What If analysis on the Release Forecasting Page
- Release Forecasting
- Release Forecasting Video
- Why don't Estimates reconcile between my Release Forecasting and Estimate Trend reports?
Background
How does VersionOne calculate the 'forecast' release completion date?
Answer
The following table describes the input fields used manually calculate the predicted release date.
Field Inputs | Calculations |
Periods | It's helpful to start by calculating period start and end dates. Period 1 Start Date = Start Date (from inputs) Period 2 Start Date = Period 1 Start Date + Period (from inputs) ...And so on |
Remaining Estimate | Remaining Estimate = Open Estimate as of current date PLUS any Closed Estimate that has been closed in the Current Period
|
Projected Velocity | Projected Velocity = Average of Closed Estimate in the previous 3 completed periods
|
Additional Periods to Completion (let's call this number N) | Additional Periods to Completion = Remaining Estimate / Projected Velocity
|
Forecast Completion | Forecast Completion = End Date of the Nth period
|
Other items of note |