Program Predictability Report

Shows the percentage of business value delivered for each team within each release (or PI).

Overview

The Program Predictability Report shows the percentage of business value delivered for each team within each release (or PI). This report is driven by the association of Backlog Goals (or Objectives) with specific portfolio items or backlog items that each team is working on. A business value (typically a 1-10 value) can be assigned to each Backlog Goal/Objective during release planning and then upon delivery the actual business value delivered is assessed. This report rolls up the total for each team and also calculates a summary total across teams.

The business value score on the report may exceed 100% if a team delivers on stretch objectives in addition to any "committed" (or non-stretch) objectives.

Generating the Program Predictability Report

  1. Choose one of the following:
    • Click Release Planning > Release Scheduling, and then select Program Predictability from Reports drop-down list.

    • Click Reports, scroll to the Project/Release Reports section, and then click Program Predictability.

  2. Select any of the filters below, and then click Go.

    • To clear filters, click Reset.

Report Filters/Parameters

  • Team: Shows Team-specific data for the project or program. The default value is "All" or "Blank".
  • Start Date: The first date the report begins calculating data.
    • For project-based reports, the default start date is the project start date.

    • For sprint/iteration-based reports, the default start date is the sprint/iteration start date.

    • For member-based reports, the default start date is 13 weeks prior to the current date.

    • If the start date is set to the current date or later, no data displays.

 