Workitem Trend Report

Editions

This feature is available in all editions.

editions-all.png

Overview

The Workitem Trend (formerly called the Release Estimate Trend Report) report shows changes in the total amount of Estimate, the amount completed (closed), and the amount remaining (open) within a release/project over a period of time. 

report_estimate_trend2.png

The total amount remaining should trend downward over time, while the amount completed should trend upward. Changes to the total estimates occur because new items are added/removed or existing estimates change.

Prerequisites

  • All VersionOne trend reports require at least two data points. If not enough data is available, the report may be blank.  Depending on the duration you select in the filters, at least one complete period of data must be available to draw a trend line. When selecting days, this means that the minimum duration is actually 2 days, which will include 2 data points.

  • Your Show Weekend report settings may affect how much data is selected.  For example, if you choose two days as duration and one day is a Saturday or Sunday, and you have elected to not Show Weekends, then you may not have sufficient data to show a trend.

Viewing the Release Estimate Trend Report

  1. On the main menu, select:

    • Reports > Workitem Trend (in the Project/Release Reports, Iteration Reports, or Planning Reports section), or

    • Release Planning > Release Scheduling >select Workitem Trend from the Reports drop-down menu.

  2. Select the report filter options, and then click Go.

Report Filters/Parameters

  • Sprint/Iteration: Shows data assigned to the sprint/iteration. The default value is "All".
  • Team: Shows Team-specific data for the project or program. The default value is "All" or "Blank".
Backlog Group:
Shows data assigned to the selected backlog group.
  • Workitem: Shows data for a specific work item type: All (all workitems), StoriesDefects, or Testsets. The default option is "All".
  • Strategic Theme: Allows you to narrow the report to focus on the items that support a given strategic theme.
  • Portfolio Item: Shows work items in the selected portfolio item and all of it's children. The default option is "Blank" and shows all work items.
  • Aggregation Type: Determines how the data is aggregated.  Valid values are:
    • Total Estimate - Sum the Estimate values. 

    • Workitem Count - Count of work items regardless of estimate value. 

  • Start Date: The first date the report begins calculating data.
    • For project-based reports, the default start date is the project start date.

    • For sprint/iteration-based reports, the default start date is the sprint/iteration start date.

    • For member-based reports, the default start date is 13 weeks prior to the current date.

    • If the start date is set to the current date or later, no data displays.

  • Duration: The number of days, weeks, or months to display.

    • For project-based reports, the default duration is the number of weeks from
      the project's start date to today.

    • For sprint/iteration-based reports, the default duration is the number of days in the
      sprint/iteration.

    • For member-based reports, the default duration is 13 weeks.

    • The report ends at the current date, so if the selected start date and duration
      extend past the current date, no data displays after the current date.

  • Show All Projects: Check this box to include all projects in the report.