How do I move a backlog item to a different project?

Question

How do I move a workitem to another project?

Answer

There are a few different ways to move an item to another project.

Option 1: Use Move to Project Button in the Grid

  1. Go to the backlog grid and locate the items you want to move.

  2. Click on the checkbox to select the backlog item.
    ProjectMove.png

  3. Click the down arrow on the Move to Project button.

  4. In the resulting pop-up, select the project you want to move these items to and then click Move.

Option 2: Change the Project on the Details Page

  1. Open the Details view of a backlog item/story, and then click the Edit button.

  2. Click the drop-down on the Project field, and then select a new project.

  3. Click Save.
    move_to_project_2.png

Option 3: Make the Project Field Editable in the Grid

  1. On the backlog item grid, double-click the Project column. The Project field will now be editable on everything listed.

  2. In each row, select a project from the drop-down list, and then click Save