Copy Projects to Another Instance

Q: We are looking to make a copy of a project in V1 for training purposes. Is there an easy way to go about doing this? The best I’ve been able to come up with is copying all the stories and moving them into a new project space, but I was wondering if there was a simpler way.

 

A: You can export and than re-import the data into the new project. Any data that you want to include, you would need to add those columns to the grid...

There is the option of our Services Team doing this task for you, but that would be a fee based service. 

For more info on how to Export workitems:

- Exporting/Downloading Grid Workitems to Excel

For more info on how to Import workitems:

Importing Stories, Defects, and Other Data from Excel

Importing a data sheet that was exported from a grid is a complex process and requires considerable manipulation of the data to make it import-able. Please contact VersionOne Support if you have any questions.