How do I include vacations into release forecasting?

Editions

This feature is available in Enterprise and Ultimate editions.

editions-eu.png

Related Articles

InternalError: HTTP Status: BadRequest(400) [MindTouch.Dream.DreamResponseException] (click for details)
Callstack:
    at wiki.search()
    at (Template:V1/AllArticlesByTag), /content/body/pre, line 5, column 12
    at template()
    at (VersionOne/VersionOne_Basics/Common_Questions/How_do_I_include_vacations_into_release_forecasting?), /content/body/div[1]/pre[2], line 2, column 9

Background

When planning a project not all the our developers are available 100% of the time during every sprint (e.g. vacation, out of the office, etc.). How do I incorporate this into the release forecasting to get a more accurate forecast?

Answer

In VersionOne, you cannot directly incorporate team member schedules into a project.

As a workaround, you can go to Capacity Planning and decrease the team member's capacity so they are not over assigned. For example, if a person's normal workload is 40 points/hours, you could decrease it to 32 points/hours if they have a day off in the week. That way, those hours will not be reflected in your release forecast.